CERN Trajectory
Measurement System
Project
Status
|
Project
|
CERN-TMS
|
|
Date
|
2007-04-19
|
|
Reference
|
Cern-tms/status-3
|
|
Author
|
Terry Barnaby
|
1.Overview
The PUPE hardware PCB's are about to have the components
installed, all of the external system hardware has arrived and is
under test, The Firmware and Software continues in development. There
has been a slight slipping of the schedule due to delays in the PUPE
boards PCB production.
2.Work Done
The following work has been performed:
The TMS cPCI racks, Module Controllers and Network switch has
arrived. This completes delivery of all of the hardware from
external vendors.
The Linux system for the Network boot Module Controllers and
System Controller's is now complete and has been installed and
tested on the actual TMS hardware including the System Controllers
and Module Controllers.
The first pass TMS software is now complete and runs in a
limited simulation mode on the TMS system hardware
We have implemented a simple GUI and a command line control
application to aid with testing the system and to act as a control
and test interface for CERN.
We have created some basic test signals and a simple FPGA
State table generator to configure the FPGA PLL State and Phase
tables for test purposes.
We have built the test leads and level shifting system to
allow the TMS Signal Generator to connect directly to the PUPE
engines for system testing.
The PUPE board PCB's have arrived, slightly later than
expected. Unfortunately there was a slight placement problem with
the cPCI connectors resulting in an additional short delay. The
Board should have the components installed early next week. Later
next week we will know the functional status of the PUPE boards.
The PUPE FPGA design is now awaiting the PUPE hardware for
integration and test.
3.Parts Arrived
The following TMS hardware has arrived from vendors:
4 x Compact PCI Module controllers, Completing the delivery.
2 x cPCI Full Racks.
2 x cPCI Part racks for development, test and support.
1 x Network Switch.
All external parts have now arrived.
4.Current Schedule
The project schedule is slightly behind the schedule stated last
month. The detailed project schedule is at:
https://portal.beam.ltd.uk/support/cern/schedule.php.
The main risk for delay is how well the first PUPE engine hardware
boards function.
The basic schedule information is:
|
Major TMS components arrive
|
March 9th
|
|
CPIC racks arrive
|
March 30th
|
|
PUPE Hardware prototype boards working
|
March 30th
|
|
PUPE FPGA firmware Alpha level
|
April 6th
|
|
PUPE Software Alpha level
|
April 6th
|
|
Pre-Series Unit Complete
|
May 4th (Likely to be delayed until May 11th)
|
|