CERN Trajectory
Measurement System
Project
Status
|
Project
|
CERN-TMS
|
|
Date
|
2007-03-09
|
|
Reference
|
Cern-tms/status-2
|
|
Author
|
Terry Barnaby
|
1.Overview
Work on the PUPE hardware, the PUPE FPGA Firmware and TMS Software
continues and some of the basic system components has arrived.
2.Work Done
The following work has been performed:
The Linux system for the Network boot Module Controllers and
System controller's has now been finalised and is fairly complete.
We need to test the Module Controllers OS on the actual hardware
when available and document the installation of the system.
RPM packages of all of the system software and TMS software
have been produced. These are in-complete at the moment but will
form the basis of the packaged software.
We have been working on the TMS software API, the tmsControl
application and the tmsPuControl applications. These applications
now have basic functionality in simulation mode.
We have tested and setup the System Controllers for operation
and are now using these within the Software development process.
We have been working on the software interface to the PUPE
FPGA API.
The PUPE board is placed and is routing as we speak. It
should pop out of layout early next week and we will have to get it
fabricated. This will mean the end of March for assembly or the
first week in April. We'll expedite as much as possible.
The PUPE FPGA design is progressing well. It has now been
built for the target Virtex-4 FPGA for test purposes.
3.Parts Arrived
The following TMS hardware has arrived from vendors:
The additional PCI Module controller's should be delivered by the
end of the second week in March. The cPCI racks have been delayed
until around March 30th due to availability of the
backplanes. The vendor is looking to see if they can provide a 4 slot
backplane for initial test purposes in case there is a further delay.
4.Current Schedule
The project schedule is on track based on the updated schedule
stated last month. The detailed project schedule is at:
https://portal.beam.ltd.uk/support/cern/schedule.php.
The basic schedule information is:
|
Major TMS components arrive
|
March 9th
|
|
CPIC racks arrive
|
March 30th
|
|
PUPE Hardware prototype boards working
|
March 30th
|
|
PUPE FPGA firmware Alpha level
|
April 6th
|
|
PUPE Software Alpha level
|
April 6th
|
|
Pre-Series Unit Complete
|
April 20th (Likely to be delayed until May 4th)
|
|