CERN Trajectory
Measurement System
Project
Status
|
Project
|
CERN-TMS
|
|
Date
|
2007-02-06
|
|
Reference
|
Cern-tms/status-1
|
|
Author
|
Terry Barnaby
|
1.Overview
We have now had official acceptance of the TMS design from CERN.
Work on the PUPE hardware, the PUPE FPGA Firmware and TMS Software
has been going on while awaiting design acceptance.
2.Work Done
The following work has been performed:
The TMS test signal generator hardware has been purchased.
The TMS test signal generator, TmsSigGen, has been produced.
Information on this is at:
https://portal.beam.ltd.uk/support/cern/doc.
This will produce the main timing and analogue test signals for the
TMS system to aid development and testing. Extra test signals will
be added as required later in the project.
We have been working on the Linux system for the Module
Controllers and System controller.
We have been working on the TMS software API.
The PUPE's circuit design has been worked on and is near
completion. Is at the start of layout with a preliminary mechanical
outline and very basic placement has been received from Layer16.
Schematics are almost complete but need some tweeks around the FPGA
clocks. The bill of materials is being prepared for manufacturing
review.
The PUPE's digital input front panel connections to the PUPE
are being developed. We have some cables for evaluation from Samtec
using tiny 50 Ohm connections but these appear fragile. We are going
to order up MCX to bulkhead SMA for development. We have started on
the design on the digital timing input cables which will likely be
MCX to LEMO-00. (MCX use less space on the board and things are
tight!).
The PUPE FPGA design has been worked on. All modules are
substantially complete. Testbench for single channel core and for 3
core complete design build. Testbench data files, and timing signals
need to be verified as realistic by CERN. Diagnostic debug signals
also to be modified by CERN. Some Top Level IO and Timing Issues to
be resolved. No external ADC connection (only SDRAM test mode input)
or external control pins yet implemented. HAIL wrapper requires some
modification to support the external signals.
3.Parts Ordered
The following TMS hardware has been ordered from vendors:
These should be delivered by the end of the second week in March.
4.Current Schedule
The detailed project schedule has been updated due to the delay in
getting the design acceptance. The detailed project schedule is at:
https://portal.beam.ltd.uk/support/cern/schedule.php.
The basic schedule information is:
|
Major TMS components arrive
|
March 9th
|
|
PUPE Hardware prototype boards working
|
March 30th
|
|
PUPE FPGA firmware Alpha level
|
April 6th
|
|
PUPE Software Alpha level
|
April 6th
|
|
Pre-Series Unit Complete
|
April 20th (Likely to be delayed until May 4th)
|
|